81、 [单选] 一位先前不活跃的干系人参与程度突然增加,这种意外的参与导致了一些变更请求。项目经理应该做什么?
The involvement of a previously inactive interested party suddenly increased, and this unexpected participation led to some change requests. What should the project manager do?
A:向干系人解释变更请求过程
Explain the change request process to interested parties
B:审查已批准的有关干系人请求的期望
Review approved expectations regarding stakeholder requests
C:与该干系人开会,以评估变更请求
Meet with the interested party to evaluate the change request
D:要求干系人与发起人讨论这些请求
Ask interested parties to discuss these requests with the sponsor
C