1. A PDM schedule is simply a bar chart with connecting lines and arrows that shows which bars are tied to other bars, logically. Briefly explained, if you can draw a bar chart, then you can draft a PDM schedule, probably on the computer.
2. Budgets and accounting systems that compare planned expenses and revenue to actual expenses and revenue are an effective way of monitoring results—after the facts and events have already occurred.
Schedules (defined as planned performance sequences) are an excellent way of measuring future results.
Schedule不但可以用来预测未来的结果,而且还是一种法律证据:
But more than that, the prebid or preconstruction PDM schedule is proof-positive of precisely what is planned and intended by the contractor when a project is bid or before it starts.
Later, when unforeseen delays, interferences, shutdowns, change orders, work sequence changes, and a host of other noncontractor-caused problems are encountered, the effects of those unplanned, unforeseen events can be readily noted by adding them to the PDM schedule as they occur. An after-the-fact, actually performed schedule is called an as-built schedule.
As-built schedules, when compared to as-bid or as-planned schedules, provide what attorneys refer to as entitlement arguments, documented proof for the payment of monetary damages. Without any as-bid, as-planned, and as-built schedules, there are no entitlement proofs and, thus, there can be no damages due the contractor for hours, days, weeks, months, and even years wasted on what was perceived to be a clean, money-making project until all the problems began.
Schedules are not the only way to prove entitlements for damages, but they are miles ahead of whatever is in second place.
本文对比了PDM(Precedence Diagramming Method)与ADM(Arrow Diagramming Method),并强调了PDM在CPM(Critical Path Method)进度计划中的优势。文章指出PDM进度计划不仅便于绘制,而且作为法律证据,能够有效记录合同方在项目投标或开始前的具体计划和意图。当遇到不可预见的问题时,通过将这些问题添加到PDM进度计划中,可以清晰地显示这些问题的影响。
817

被折叠的 条评论
为什么被折叠?



