Scope management means figuring out what's out of scope, not just what's part of scope.

five scope management processes:
1. scope planning
output: scope management plan

2. scope definition
output:scope statement
scope definition tools&techniques:stakeholder analysis,product ayalysis,alternatives idenfication,expert judgment

3. create WBS(Work Breakdown Structure)
Project is broken down by phase or deliverable.
A WBS can be structued any way it make sense to you and your project team.
Work package is a unit of work in the WBS.
The WBS dictionary is a description of each work package listed in the WBS.
tools&techniques: decomposition and templates&forms of similar past project
output: work breakdown structure, WBS dictionary, scope baseline,updates to the scope statement, updates to the scope management plan, change requests

4. scope change
It describes how specific approved changes are used to update the project documents

5. scope verification
to gain formal acceptance of the project deliverables from the sponsor and stakeholders
tools: inspection
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值