Some element of PMP
PMI-project manage of institute
Project have follow features:
temporary;unique;PDCA-plan do check act
Projects and operations differ primarily in that operations are ongoing and repetitive, while projects are temporary and unique.
The default organization can be defined matrix type.
Portfilo/project group focus on strategy; Programs/project set focus on revenue; Project always pay attention to product; Subproject follow with interest UI design, code written, system testing etc.
EEF-enterprise environmental factors.
Impact element in project: risk, process, resource, range, cost, related satisfaction;
Project life cycle: begin project, organization and prepare, execute project, close project;
Project management process group:
Start-up; Planning; Executable; Monitoring; Wind up;
Each process contained input, tools and technology, output.
Professional ethics: responsibility;honesty; notarization; respect.