Let’s begin with defining the Reserves: Reserves are the amount of fund, time, or resources that are estimated from the risk management processes.

PMBOK® Guide Fifth Edition defines reserves as:

“A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g. Management reserve contingency reserve) to provide further detail on what types of risk are meant to be mitigated.”

As a further explanation, in a project all the work performed as per project identified performance measurement baselines which include scope, schedule and cost baselines. In other words, work is performed for the identified scope with corresponding scheduling and cost of each item in the scope.

As every project result in a unique product, service or result, that’s why we need to consider the uncertainties involved in the project. These uncertain events may affect our ability to achieve project objectives, that’s why reserves are a mechanism to deal with cost and schedule risks.

There are two types of uncertainties involved in the project:

  1. Known- Unknown: These uncertain events are identified using “Identify Risks” process, but the amount to which they can affect project objectives is not predictable with a reasonable degree of confidence, known as Known-Unknown risks. After risk and their priority identification, risk response plans are applied using “Plan Risk Responses” process. Risk remains after applying risk response strategies are residual in the risk register. A reserve is identified for these residual risks and known as contingency reserves.
  2. Unknown– Unknown: Some risks are not identified using “Identify Risks” process and we are not aware about their identity, amount of probability and time of their occurrence, known as Unknown-Unknown risks. Management reserves are defined to deal with these kinds of risks which are not mentioned in the risk register.

 

PMBOK® Guide Fifth Edition defines reserves as:

Contingency Reserve: Budget within the cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for which contingent or mitigating responses are developed. “

Management Reserve: An amount of the project budget withheld for management control purposes. These are budgets reserved for unforeseen work that is within scope of the project. “

The management reserve is not included in the performance measurement baseline (PMB).

Below mentioned diagram shows difference between contingency and management reserve in the context of performance measurement baseline:

Contingency-and-Management-Reserve

Difference between Contingency and Management Reserves:

Contingency Reserves Management Reserves
Designed to deal with Known – Unknown uncertainties Designed to deal with Unknown-Unknown uncertainties.
Developed for the accepted risks remains after applying mitigation, risk response strategies; these are residual risks in the risk register. Developed for unforeseen events and these are not mentioned in the risk register
Contingency reserves are included in the performance measurement baseline Management reserves are not included in the performance measurement baseline.
These reserves are used when residual and/or an accepted risk occurs. Management reserves are used when unforeseen events occur. The amount of time and cost used to account unforeseen work is added to the project performance baseline.
When we move towards project execution, more specific information about the project become available and these reserves may get reduced or eliminated. When accepted risks occur, these reserves are used. When we move towards project execution these reserves are used when unforeseen risks occurs.
The project manager has complete authority about the usage of these reserves A formal approval from project sponsor may be required for the usage of management reserve

 

As to recollect:

Contingency Reserve is a cushion for the remaining risks which ensures that if they become reality this reserve should be able to absorb the impact and project team still can deliver in baseline time and duration.

As these are included in the performance measurement baseline, the project manager has authority on their usage. These reserves are used for already identified events and based on availability of precise information as project move through execution; these reserves may be used, reduced or eliminated.

Management Reserve is a kind of reserve to fund unforeseen events, as these are not included performance measurement baseline, their usage may require the involvement of the project sponsor.

Management reserves are included in the project budget and the amount depends on various factors like the ability to recognize customer nature, the complexity of the project etc. Historical records play significant role in designing management reserves.  If you are developing the type of product first, time you may need more reserve. In most of cases a certain percentage of the total identified project cost is allocated as management reserves like 5% of total project cost, again it depends on various above mentioned factors.

I hope this blog has sufficiently answered your all queries related to what are Contingency Reserves and Management Reserves and the basic differences underlying them. Good Luck with your PMP® Certification Exam.

资源下载链接为: https://pan.quark.cn/s/22ca96b7bd39 在当今的软件开发领域,自动化构建与发布是提升开发效率和项目质量的关键环节。Jenkins Pipeline作为一种强大的自动化工具,能够有效助力Java项目的快速构建、测试及部署。本文将详细介绍如何利用Jenkins Pipeline实现Java项目的自动化构建与发布。 Jenkins Pipeline简介 Jenkins Pipeline是运行在Jenkins上的一套工作流框架,它将原本分散在单个或多个节点上独立运行的任务串联起来,实现复杂流程的编排与可视化。它是Jenkins 2.X的核心特性之一,推动了Jenkins从持续集成(CI)向持续交付(CD)及DevOps的转变。 创建Pipeline项目 要使用Jenkins Pipeline自动化构建发布Java项目,首先需要创建Pipeline项目。具体步骤如下: 登录Jenkins,点击“新建项”,选择“Pipeline”。 输入项目名称和描述,点击“确定”。 在Pipeline脚本中定义项目字典、发版脚本和预发布脚本。 编写Pipeline脚本 Pipeline脚本是Jenkins Pipeline的核心,用于定义自动化构建和发布的流程。以下是一个简单的Pipeline脚本示例: 在上述脚本中,定义了四个阶段:Checkout、Build、Push package和Deploy/Rollback。每个阶段都可以根据实际需求进行配置和调整。 通过Jenkins Pipeline自动化构建发布Java项目,可以显著提升开发效率和项目质量。借助Pipeline,我们能够轻松实现自动化构建、测试和部署,从而提高项目的整体质量和可靠性。
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值