Has a bug in oracle bpel, it is fixed duration by expression

项目需求中提到的任务在十天内完成,但未考虑周末等非工作日。作者实现了一个XPath函数来解决此问题,但在固定持续时间表达式中遇到了bug。与Oracle工作人员沟通后确认了这一问题的存在。

摘要生成于 C知道 ,由 DeepSeek-R1 满血版支持, 前往体验 >

          our project has a demand,staffer promises proposer that task would be dealed in ten days ,this  is a duration in bpel task. but  in these days, mybe have weekend days, that is not work days .we must caculate how many weekend days in duration days ,then add those days to duration days.

          I implemented IXPathFunction  interface, test it ,it is working. but put this xpath function into fixed duration by expression place .it does not working . after communicated with oracle staffer.the answer is that it is a bug!

          hope, be resolved ASAP!