UAW计算过程
| 序号 | actor复杂度级别 | 权值 | 参与角色数 | UAWi |
| 1 | simple | 1 | 1 | 1 |
| 2 | average | 4 | 1 | 4 |
| 3 | complex | 3 | 2 | 6 |
| 总计 | 11 |
UUCW计算过程
| 序号 | 用例复杂度级别 | 权值 | 用例数量 | UUCW |
| 1 | simple | 5 | 5 | 25 |
| 2 | average | 10 | 7 | 70 |
| 3 | complex | 12 | 5 | 60 |
| 总计 | 155 |
因此,UUCP=UAW+UUCW=11+155=166
TCF
| 序号 | 技术复杂度因子 | 权值 | value值 | TCF |
| 1 | TCF1 | 2 | 2 | 4 |
| 2 | TCF2 | 1 | 4 | 4 |
| 3 | TCF3 | 1 | 6 | 6 |
| 4 | TCF4 | 2 | 2 | 4 |
| 5 | TCF5 | 2 | 3 | 6 |
| 6 | TCF6 | 1 | 3 | 3 |
| 7 | TCF7 | 1 | 5 | 5 |
| 8 | TCF8 | 1 | 3 | 3 |
| 9 | TCF9 | 1 | 2 | 2 |
| 10 | TCF10 | 2 | 3 | 6 |
| 11 | TCF11 | 1 | 6 | 6 |
| 12 | TCF12 | 1 | 4 | 4 |
| 13 | TCF13 | 1 | 1 | 1 |
TCF=0.6+0.01*(4+4+6+4+6+3+5+3+2+6+6+4+1)=1.04
ECF
| 序号 | 环境因子 | 权值 | value值 | ECF |
| 1 | ECF1 | 1 | 4 | 4 |
| 2 | ECF2 | 1 | 5 | 5 |
| 3 | ECF3 | 2 | 3 | 6 |
| 4 | ECF4 | 1 | 2 | 2 |
| 5 | ECF5 | 2 | 4 | 8 |
| 6 | ECF6 | 1 | 1 | 1 |
| 7 | ECF7 | 1 | 1 | 1 |
| 8 | ECF8 | 1 | 2 | 2 |
ECF=1.4-0.03*(4+5+6+2+8+1+1+2)=0.53
UCP=UUCP*TCF*ECF=166*1.04*0.53=91.4992
Effor=PF*UCP=20*91.4992=1830工时=229天/人
博客介绍了UCP(Use Case Points,用例点)及工作量的计算过程。先计算UUCP(未调整的用例点),由UAW和UUCW相加得出;接着计算TCF(技术复杂度因子)和ECF(环境复杂度因子);最后算出UCP,并根据公式得出工作量为229天/人。