The overall manufacturing planning process is comprised of:

  • The forecast values and requirements from the sales information system and costing/profitability analysis are inputs to the Sales and Operations Planning (SOP) phase in which independent requirements are determined.
  • Master Schedule items (those items that greatly influence profits or consume critical resources ) are planned. Planning the master schedule items separately leads to a reduction in stock levels and improved delivery performance.
  • Materials requirements planning (MRP) is the final step in the planning process. The output of MRP is either a planned production order, a purchase requisition, or a planned purchase order.

The overall manufacturing execution process is comprised of:

  • Production orders are released
  • Materials are issued
  • Completion confirmations are performed
  • Goods are received into stock.

The manufacturing process affects capacity, costing inventory, reporting, and analysis.

The five primary phases are:

  • Sales and operations planning
  • Demand management
  • Master production planning
  • Materials requirements planning
  • Production order execution
Sales and Operations Planning (SOP)

The forecast values and/or requirements from customer order management, sales information system, and controlling are inputs to the sales and operations planning phase.

The main steps in sales and operations planning are:

  • Creating a sales and production plan--Methods
    • Manual entry
    • Forecast of consumption
    • Copying data from financial modules
    • Copying data from the sales information system
    • transferring product group
  • Disaggregating the planning values
  • Transferring the planning values to demand management

There are four ways to create a production plan in the system.

  • Based on sales
  • Based on target inventory
  • Based on current days of sales supply
  • Based on running down the inventory to zero (Just in Time or Kanban)
Demand Management

Demand management links top-level requirements planning (SOP) with materials planning (MPS and MRP)

  • Demand Management determines the requirements dates and quatities for important assemblies and specifies the strategies for planning and producing or procuring finished products.
  • The result of Demand Management is the demand program
  • The demand program distinguishes planned independent requirements and customer independent requirements
  • The requirements can then be transferred to MPS or directly to MRP depending on the MRP type selected in the material master of the material.
MPS Master Production Scheduling

The independent requirements from Demand Management initiate the master scheduling process for MPS designated items

The master production schedule is the anticipated build schedule (high level)

  • The purpose of MPS and MRP is to guarantee availablility
  • The MPS run results in planned orders for the master schedule items and dependent requirements for the level directly below the MPS items.
  • MPS = Finished goods level only
MRP Materials Requirements Planning
  • In material requirements planning (MRP), the system calculates the net requirements while considering available warehouse stock and scheduled receipts from purchasing and production.
  • The uses of MRP are as follows:
    • MRP is used to plan the on time production or procurement of the required quantities for both internal consumption and customer demand.
    • This process involves monitoring stock levels and automatically creating order proposals for purchasing and production.
    • For materials produced in-house, the dependent requirements of teh conponenets are determined during BOM explosion.
    • BOM explosion is the process by which the system calculates the componenets or assemblies required to produce the material.
  • MRP requires exact requirement quantities, which allows you to work with particularly low safety stocks.
  • The output of MRP is either a planned production order, a purchase requisition, or a planned purchase order.
  • A planned order can be converted to a production order (for materials produced in-house) or a purchase requisition for procured materials.
MANUFACTURING EXECUTION

Manufacturing Execution is intitated by releasing each production order to the shop floor.

Production Orders: Contents
  • Production orders are used:
    • To control and monitor production within a factory
    • As a controlling instrument for cost accounting
  • The production order displays:
    • what and how much is to be produced (including duration)
    • when production is to be executed
    • what is required for production (components, resources)
    • which method of production to be used
    • the capacities required e.g. machine, labor
    • production costs
Production Order Execution Process
  • Production orders go through a series of steps including:
    • Production order release
    • Goods issue (issuing the components or raw materials)
    • Completion confirmation confirming that the final material is complete
    • Goods receipt (receiving the finished good back into inventory)
    • Order settlement
 来源: http://www.onestopsap.com/MPE/
资源下载链接为: https://pan.quark.cn/s/d9ef5828b597 在本文中,我们将探讨如何通过 Vue.js 实现一个带有动画效果的“回到顶部”功能。Vue.js 是一款用于构建用户界面的流行 JavaScript 框架,其组件化和响应式设计让实现这种交互功能变得十分便捷。 首先,我们来分析 HTML 代码。在这个示例中,存在一个 ID 为 back-to-top 的 div 元素,其中包含两个 span 标签,分别显示“回到”和“顶部”文字。该 div 元素绑定了 Vue.js 的 @click 事件处理器 backToTop,用于处理点击事件,同时还绑定了 v-show 指令来控制按钮的显示与隐藏。v-cloak 指令的作用是在 Vue 实例渲染完成之前隐藏该元素,避免出现闪烁现象。 CSS 部分(backTop.css)主要负责样式设计。它首先清除了一些默认的边距和填充,对 html 和 body 进行了全屏布局,并设置了相对定位。.back-to-top 类则定义了“回到顶部”按钮的样式,包括其位置、圆角、阴影、填充以及悬停时背景颜色的变化。此外,与 v-cloak 相关的 CSS 确保在 Vue 实例加载过程中隐藏该元素。每个 .page 类代表一个页面,每个页面的高度设置为 400px,用于模拟多页面的滚动效果。 接下来是 JavaScript 部分(backTop.js)。在这里,我们创建了一个 Vue 实例。实例的 el 属性指定 Vue 将挂载到的 DOM 元素(#back-to-top)。data 对象中包含三个属性:backTopShow 用于控制按钮的显示状态;backTopAllow 用于防止用户快速连续点击;backSeconds 定义了回到顶部所需的时间;showPx 则规定了滚动多少像素后显示“回到顶部”按钮。 在 V
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值