Schedule Problem |
| Time Limit: 2000/1000 MS (Java/Others) Memory Limit: 65536/32768 K (Java/Others) |
| Total Submission(s): 48 Accepted Submission(s): 18 |
|
Problem Description
A project can be divided into several parts. Each part should be completed continuously. This means if a part should take 3 days, we should use a continuous 3 days do complete it.
There are four types of constrains among these parts which are FAS, FAF, SAF and SAS. A constrain between parts is FAS if the first one should finish after the second one started. FAF is finish after finish. SAF is start after finish, and SAS is start after
start. Assume there are enough people involved in the projects, which means we can do any number of parts concurrently. You are to write a program to give a schedule of a given project, which has the shortest time.
|
|
Input
The input file consists a sequences of projects.
Each project consists the following lines: the count number of parts (one line) (0 for end of input) times should be taken to complete these parts, each time occupies one line a list of FAS, FAF, SAF or SAS and two part number indicates a constrain of the two parts a line only contains a '#' indicates the end of a project |
|
Output
Output should be a list of lines, each line includes a part number and the time it should start. Time should be a non-negative integer, and the start time of first part should be
0. If there is no answer for the problem, you should give a non-line output containing "impossible".
A blank line should appear following the output for each project. |
|
Sample Input
3 2 3 4 SAF 2 1 FAF 3 2 # 3 1 1 1 SAF 2 1 SAF 3 2 SAF 1 3 # 0 |
|
Sample Output
Case 1: 1 0 2 2 3 1 Case 2: impossible |
|
Source
Asia 1996, Shanghai (Mainland China)
很明显的差分约束,找到约束条件就好了
FAS 第一个的结束 应该在 第二个的开始 之后。 f(u) + a[u] >= f[v]. ---> f(u) - f(v) >= -a[u]
FAF f(u) + a[u] >= f(v) + a[v] ---->. f(u) - f(v) >+ a[v] - a[u]
SAF f(u) >= f(v) + a[v] ---->. f(u) + f(v) >= a[v]
SAS f(u) >=. f(v) --->. f[u] - f[v] >= 0
通过题意来找到约束的范围,这个题是要求最长路,也就是 约束范围最小 是最长路的值
|
hud-1534 Schedule Problem(差分约束)
最新推荐文章于 2021-07-28 10:07:37 发布
本文介绍了一个项目调度问题,包括四种不同类型的任务约束(FAS、FAF、SAF 和 SAS),并提供了一种算法来确定项目的最短完成时间。通过差分约束的方法找到了不同任务之间的约束条件。
2万+

被折叠的 条评论
为什么被折叠?



