Activity Types(work center ; cost center)

本文介绍了如何通过配置活动类型来实现成本中心的成本分配,并详细解释了活动类型与工作中心之间的关系。通过具体案例展示了当成本中心未分配活动类型时可能遇到的问题及解决方案。

Activity Types

Activity types are used to describe the various forms of activity that are performed at a cost center.

Activity types are valuated for each cost center and period with a charge rate that consists of a fixed portion and a variable (work-related) portion. Thus the costs incurred at a cost center can be distributed to products, according to which activities have been performed.

You can assign each standard value in the work center an activity type as a default

Relationships between the Cost Center, Activity Types, Work Center and Routing

The following graphic illustrates the relationships between cost center, activity types, work center and routing for costing internal activities.

 

This graphic is explained in the accompanying text

Relationships between the Cost Center, Activity Types, Work Center and Routing

The "Production" cost center has been assigned four activity types. Each activity type was valuated with a charge rate that is made up of a fixed and a variable (work-related) part. In this example, a setup hour (SET) costs $70.

Since the work center is assigned to a cost center, the activity types (as long as permissible in the cost center) can be assigned to standard values in the work center. In this example the activity types SET, MAC and LAB are assigned to the standard values "Setup", "Machine" and "Labor" in the "Milling machine 5" work center. These activity types are then suggested when the work center is assigned to a routing

In the work center a formula can also be assigned to each standard value for costing. Formulas are used to calculate activities for the operation quantity from the general operation data and the standard values.

The activity types are used to calculate the costs for these activities.

case案例分析解决(work center and activ):

Hi,
in trx CR02 when I click on F4 button to select an activity type in costing view, system prompts:

"No activity types assigned to cost center 7000, controlling area EL80 on 06.04.2011"

 

solution;

Hi!
I've done finished this issue!

Please follow steps below:
1. Create activity type in T-Code: KL01
2. Go to KP26 to create the realtionship between Cost Center and Activity.

Now you can see new activity in Costing tab.

 

 

转载于:https://www.cnblogs.com/jefflu2012/p/3209607.html

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值