How to perform a WIP job Completion in Oracle MES ,Below is basic flow for completion.
Define BOM,and Routing, Then Create a Job in Oracle Application(Supply type:Assembly Pull for this demo case)

Responsibility:MES Supervisor, Enter the organization,then press 'Start' button

Action:Search Jobs,And Go

Search your job name, You will see the job details. Now we need move transaction.(Queue:3)

After express move, you will see,'To Move' got changed to 3,and 'Queue' is zero.Now we can complete Job

Input Lot Detail if any,Then continue

Since Supply type is Assembly Pull, so backflush need to be done after completion.

After pressing finish button, you will see job is complete.

本文介绍在 Oracle MES 中执行 WIP (Work in Progress) 任务完成的基本流程。主要内容包括定义物料清单 (BOM) 和工艺路线,创建作业,并通过 MESSupervisor 责任角色进行作业搜索与完成操作。作业完成后还需执行回冲处理。