6012SSL Project Management for Business (MOCK EXAM)SQL

Java Python 6012SSL

Project Management for Business (MOCK EXAM)

Section A: Answer ALL questions in this section.

Question 1.

Case Study: Renewable Energy Project

Background:

EcoPower Solutions, a renewable energy company in the UK, is developing a wind farm project in Peru (South America) to provide clean energy to a growing population. The project includes designing, installing, and commissioning 50 wind turbines in a remote region. It requires collaboration with local government authorities, international suppliers (from China and Germany), and the indigenous community.

Emma, the project manager, must ensure the project is delivered on time and within budget while addressing environmental and community concerns. The project involves several challenges, including logistical issues, environmental regulations, and cultural differences.

Questions:

A) Identify and evaluate at least three (3) main risks faced by EcoPower Solutions in this project. How can these risks impact the project’s success?

B) How can the identified risks be effectively managed using appropriate risk management strategies?

C)  Critically evaluate the role of a Risk Register in systematically

documenting, monitoring, and controlling potential risks across all phases of a project’s lifecycle.

Question 2. Critical Path Analysis (CPA)

Considering the project information presented in the table below:

Activities

Durations (days)

Predecessor

A

3

-

B

2

A

C

4

6012SSL Project Management for Business (MOCK EXAM)SQL

A

D

4

B

E

2

B

F

3

C

G

3

C

H

2

F, G

I

2

D, E

J

3

I, H

a)    Draw the network diagram

b)    Calculate the total duration of the project

c)    Identify the critical path of the project

Section B: Answer ONLY ONE question in this section.

Question 3.

In the context of project management, discuss the importance of implementing a Quality Management Plan. How does it contribute to achieving project objectives, and what are the key components that should be included in the plan? Provide examples to illustrate your answer.

Question 4.

How can the absence of a Communication Plan lead to misunderstandings and inefficiencies within a project team, and what are the potential consequences for stakeholder relationships? Provide relevant examples         

评论
成就一亿技术人!
拼手气红包6.0元
还能输入1000个字符
 
红包 添加红包
表情包 插入表情
 条评论被折叠 查看
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值